Merry Christmas  - The first steel segment lifted

December 25th, 2014 -  Christmas gift ! the first steel segment D00 is uploaded from the barge and lifted in its final position. It will be the transition part between the concrete and the steel deck. A short segment of only 4.50 m in length with a total weight of 380 to. A 1'800 to. capacity floating crane has been brought from Romania for this operation.

 

Another mobile crane of 600 to. has been installed on the platform. This crane needed 10 days of installation. A great and special event for BB3 at the end of 2014